SuperyachtNews.com - Business - Liquidated Damages Clauses

By SuperyachtNews

Liquidated Damages Clauses

Mark Needham, Partner at Hannaford Turner LLP, outlines the relevance to this industry of a recent court judgement…

The Commercial Court handed down its decision in De Havilland Aircraft of Canada Limited v Spicejet Limited [2021] EWHC 362 (Comm) on 23 February 2021. The judgment acts as a useful guide to the English court’s approach to dealing with issues relating to liquidated damages clauses in English law governed contracts.

Given the prevalence of liquidated damages clauses in the superyacht industry – particularly in Yacht Construction Agreements and in the industry-standard MYBA Charter Agreement, this note summarises the issues in dispute in the De Havilland case and the points of note for superyacht industry participants, particularly for those involved in negotiating liquidated damages clauses in Yacht Construction Agreements where liquidated damages clauses are commonplace and deposit forfeiting clauses, which sometimes arise under letters of intent and/or sale and purchase agreements.

The Background Facts in De Havilland v Spicejet

The case, brought by the Canadian Aircraft manufacturer, De Havilland, against the Indian low-cost airline, Spicejet, relates to an Aircraft Purchase Agreement for the sale of ‘Q-400’ series aircraft by De Havilland to Spicejet.

The facts, put succinctly, are:

1) Spicejet entered into a contract with De Havilland for the sale and purchase by Spicejet of 25 ‘Q-400’s. Pursuant to clause 15.4 of the Purchase Agreement, Spicejet had agreed with De Havilland that:

“15.4 In case of termination of this Agreement, in whole or in part, by Bombardier* pursuant to this Article 15:

...

(c) Bombardier shall be entitled to recover from Buyer liquidated damages for Buyer's default in the amount of $2,500,000 USD (Two Million and Five Hundred Thousand United States Dollars) for each terminated Aircraft. Buyer agrees that such liquidated damages do not constitute a penalty and are a reasonable and agreed amount of the anticipated or actual harm or damages to be suffered by Bombardier as a result of or in connection with Buyer's default. Bombardier shall give credit for any payments in respect of such terminated Aircraft which have been paid by or on behalf of Buyer, and the parties agree that Bombardier shall be entitled to recover under this Article 15.4(c) only the amount stipulated under this Article 15.4(c) after allowing such credit.

The parties agree that the remedies described in this Article 15.4 are exclusive of and in substitution for any and all other rights and remedies provided by law or otherwise for any termination of such Aircraft by Bombardier under this Article 15.

....”

(*Bombardier purchased De Havilland in 1992 - all references to Bombardier should therefore be read as references to De Havilland)

2)  Spicejet paid for and accepted delivery of the first 5 aircraft, but failed to pay the pre-delivery payments in respect of Aircraft 6 – 20 and to take delivery of Aircraft 6 – 8.

3)  De Havilland served notices terminating the individual sale and purchase agreements for the undelivered aircraft and the master Purchase Agreement and brought a claim against Spicejet in the Commercial Court in London for liquidated damages in respect of all of the undelivered aircraft in the sum of US $42.95m.

4)  In defence of De Havilland’s claims, Spicejet asserted that there was an arguable case that the liquidated damages clause in the Purchase Agreement was an unenforceable penalty clause.


The Judgment

Sir Michael Burton GBE, sitting as the High Court Judge in the case, rejected the grounds relied on by Spicejet for asserting that the liquidated damages clause of the Purchase Agreement was an unenforceable penalty and held that the liquidated damages provision should stand.

In giving judgment, Sir Michael relied heavily on earlier a number of earlier English authorities including:

1. The Supreme Court’s decision in Cavendish Square Holding BV v Talal El Makdessi [2015] UKSC 67, in particular, the following extracts of Lord Neuberger, Lord Sumption and Lord Mance’s speeches:

"32. The true test is whether the impugn provision is a secondary obligation which imposes a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation. The innocent party can have no proper interest in simply punishing the defaulter. His interest is in performance or in some appropriate alternative to performance... But compensation is not necessarily the only legitimate interest that the innocent party may have in the performance of the defaulter's primary obligation...

33. The penalty rule is an interference with freedom of contract. It undermines the certainty which parties are entitled to expect of the law. Diplock LJ was neither the first nor the last to observe that "the court should not be astute to descry a penalty clause"... As Lord Woolf said... " The court has to be careful not to set too stringent a standard and bear in mind that what the parties have agreed should normally be upheld", not least because "any other approach will lead to undesirable uncertainty especially in commercial contracts." ...
....

35. But for all that, the circumstances in which the contract was made are not entirely irrelevant. In a negotiated contract between properly advised parties of comparable bargaining power, the strong initial presumption must be that the parties themselves are the best judges of what is legitimate in a provision dealing with the consequences of breach.

...

What is necessary in each case is to consider, first, whether any (and if so what) legitimate business interest is served and protected by the clause, and, second, whether, assuming such an interest to exist, the provision made for the interest is nevertheless in the circumstances extravagant, exorbitant or unconscionable. In judging what is extravagant, exorbitant or unconscionable, I consider... that the extent to which the parties were negotiating at arm's-length on the basis of legal advice and had every opportunity to appreciate what they were agreeing must at least be a relevant factor.”

And;

2. The House of Lord’s decision in Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd [1914] UKHL 1, in particular, the speech of Lord Dunedin at 220:

"I therefore conclude that the correct test for a penalty is whether the sum or remedy stipulated as a consequence of a breach of contract is exorbitant or unconscionable when regard is had to the innocent party's interest in the performance of the contract. Where the test is to be applied to a clause fixing the level of damages to be paid on breach, an extravagant disproportion between the stipulated sum and the highest level of damages that could possibly arise from the breach would amount to a penalty and thus be unenforceable."

Taking these important authorities into account, Sir Michael held that:

1. The parties were both represented at the time (and still) by sophisticated and experienced lawyers, and were themselves substantial commercial operators in the aircraft industry with a long-standing commercial relationship, and with clearly comparable bargaining power. Issues were raised by De Havilland in the evidence as to the price for the aircraft being, on its case, particularly favourable to Spicejet, and as to the frequency of liquidated damages or forfeited deposit clauses in the aviation industry.

2. Spice Jet had every opportunity for advice, and indeed the opportunity to use its own experience, before agreeing, as it did in Article 15.4 (c), that "such liquidated damages do not constitute a penalty and are a reasonable and agreed amount of the anticipated or actual harm or damages to be suffered by [the Claimant] as a result of or in connection with Buyer's default".
3. Spicejet had not begun to satisfy the English court that the “strong initial presumption” referred to by Lords Sumption and Neuberger in Cavendish that “the parties themselves are the best judges of what is legitimate in a provision dealing with the consequences of a breach of contract” should be ignored.
4. No evidence was appropriate as to the actual loss suffered in considering whether the liquidated damages clause was enforceable. The whole purpose of a liquidated damages clause is to avoid the expense and time incurred in calculating the actual extent of loss, and mitigation is only relevant to estimating anticipated loss.
5. Spicejet had not even come close to casting doubt that the liquidated damages sum falls below the "highest level of damages that could possibly arise from the breach" as Lord Dunedin’s test required. What Spicejet was paying for each of the 25 aircraft was approximately US$ 20m (plus contractual price inflation) with pre-delivery payments due for each aircraft. 12.5% for liquidated damages was not surprising (and was agreed between the parties at the time) in respect of such highest possible loss: if an aircraft were manufactured, it might not be resold at all, or be sold at a considerably lesser price even after steps to mitigate, and not without substantial expenditure in respect of changing the specifications, and marketing, and after storage and depreciation: and if some were not manufactured, the opportunity of sale of those aircraft to other purchasers would be lost, at a considerable cost of loss of profit and wasted overheads, and the relevant manufacturing slots would have been wasted. The purpose of having a liquidated damages clause by way of pre-estimate of loss is to avoid the need to await and calculate the actual loss, and to insist on that very calculation being done in order to justify the pre-estimate wholly destroys the point. That is why the assessment by the Court is whether there is an exorbitant or extravagant pre-estimate. Spicejet had not made any attempt to cast doubt on the realistic nature of the estimate of loss, which was agreed at the time.

Key Take Away Points for the Superyacht Industry

The judgment in De Havilland Aircraft of Canada Limited v Spicejet Limited [2021] EWHC 362 (Comm) neatly summarises and reminds those drafting liquidated damages and deposit forfeiting clauses of how the English court is likely to deal with any disputes relating to the enforceability of such clauses, namely that:

1. There is likely to be a strong initial presumption in favour of finding that the sums of liquidated damages or deposit forfeit sum agreed between the parties at the time of contracting for breach of a specific provision of the contract is an acceptable amount;

2. Where the parties (i) negotiated the relevant contract with the assistance of sophisticated and experienced lawyers; (ii) are/were of comparable bargaining power; and/or (iii) had an opportunity to appreciate and understand what they were agreeing to, the court is likely to take these factors into account to the detriment of the party asserting that the liquidated damages or deposit forfeit clause should be held to be unenforceable; and

3. The amount of the actual loss suffered by the party claiming liquidated damages is unlikely to be considered in much detail by the court, unless it can be shown that the amount is extravagant, exorbitant or unconscionable. In determining whether such a sum is extravagant, exorbitant or unconscionable the court will have regard to point (2) above.

I believe it is also safe to conclude that the fact that De Havilland and Spicejet had expressly agreed that “...such liquidated damages do not constitute a penalty and are a reasonable and agreed amount of the anticipated or actual harm or damages to be suffered by Bombardier as a result of or in connection with Buyer’s default.” was of material relevance to the court.

For those in the Superyacht industry involved in drafting and negotiating liquidated damages or deposit forfeit provisions, the three key take away points in the writer’s opinion can be summarised as:

1. Be sensible and proportionate when negotiating the amount of liquidated damages payable for specified breaches of contract and/or the amount of deposit to be forfeited. Securing disproportionate or exorbitant sums for breaches of contract or failure to perform may feel like a contractual ‘win’ at the negotiating table, but in reality, it creates a situation where the clause may be struck down by the court and held to be unenforceable; and
2. Draft liquidated damages clauses with care and attention – the language used can be important;
3. Where parties agree in a contract that a sum payable as liquidated damages and/or as a deposit forfeit is reasonable, it will be difficult to persuade the court otherwise. 

 

Mark Needham

Partner, Hannaford Turner LLP

Join the discussion

Liquidated Damages Clauses

32197

To post comments please Sign in or Register

When commenting please follow our house rules


Click here to become part of The Superyacht Group community, and join us in our mission to make this industry accessible to all, and prosperous for the long-term. We are offering access to the superyacht industry’s most comprehensive and longstanding archive of business-critical information, as well as a comprehensive, real-time superyacht fleet database, for just £10 per month, because we are One Industry with One Mission. Sign up here.

Related news

Image for Become the norm, rather than the exception

Become the norm, rather than the exception

On International Women’s Day, Liz Cox shares her words of wisdom with SuperyachtNews

Business

Image for The path to a successful brokerage deal

The path to a successful brokerage deal

Adam Ramlugon, partner at Hannaford Turner, discusses the key legal considerations

Owner

Image for Inmarsat provides guidance on cyber security obligations

Inmarsat provides guidance on cyber security obligations

Inmarsat has released a report covering the IMO's new cyber security obligations and their implications for yachts

Technology

Image for The Pacific: an untapped resource

The Pacific: an untapped resource

Where do the opportunities and challenges for the superyacht market exist across the Pacific? How can the industry evolve to become truly global?

Business

Image for Marina Port Vell Barcelona to offer premium healthcare coverage

Marina Port Vell Barcelona to offer premium healthcare coverage

Marina Port Vell Barcelona signs a collaboration agreement with Quirónsalud to offer healthcare coverage

Owner

Sign up to the SuperyachtNews Bulletin

Receive unrivalled market intelligence, weekly headlines and the most relevant and insightful journalism directly to your inbox.

The SuperyachtNews App

Follow us on