Amels completes eight-month refit on 74m 'Ilona'
Dutch shipyard Amels has completed its eight-month refit on its own 74m superyacht, built by the shipyard in 2004. The refit on motoryacht 'Ilona' included the addition of a helideck and movable swimming pool.…
“The owner wanted to have a large swimming pool and a helipad large enough to take his Agusta 109 Grand New helicopter,” said the owner’s representative David McQueen. As a result, an extensive reworking of her interior and superstructure took place.
Her below-deck helicopter hangar was removed to make room for the 10m x 3m swimming pool with a movable floor, with a maximum depth of 1.5m, whilst the original pool was replaced by additional deck space. The new pool can be filled with 40,000 litres of sea water, which is purified through a filtration system, and can be heated to 6° higher than the sea temperature in an hour.
Due to the scale of the refit, much work was done to ensure the motoryacht spent minimal time in the Dutch shipyard. “Having looked through the original construction plans, we did everything possible to minimise Ilona’s time at the yard,” said Amels Managing Director Rob Luijendijk. For example, the deck extensions were pre-manufactured in advance.”
Luijendijk added: “We enjoyed the engineering challenge of modifying the superstructure such that it could handle the maximum take-off weight of the helicopter, of 3,500kg.”
It was also important for the owner that the major alterations to the 73.7m motoryacht would not affect the Redman Whiteley Dixon designed profile. “Adding the additional superstructure to accommodate the helipad would have affected the lines of the yacht, so we extended the owner’s deck and the bridge deck by two metres in order to bring the aesthetic appearance back into balance,” said Justin Redman. “We also used metallic grey paint to reduce the visual impact of the helideck, and the overall result is that the yacht, despite all the changes, looks every bit as streamlined and well-proportioned as before.”
Luijendijk concluded: “This was an enormously complex project, but we have the right people and facilities for complex projects like this.”
A video of Ilona’s new helideck in action can be viewed here.
Related Links
Amels Profile | Amels Website
Redman Whiteley Dixon Profile | Redman Whiteley Dixon Website
NEW: Sign up for SuperyachtNewsweek!
Get the latest weekly news, in-depth reports, intelligence, and strategic insights, delivered directly from The Superyacht Group's editors and market analysts.
Stay at the forefront of the superyacht industry with SuperyachtNewsweek
Click here to become part of The Superyacht Group community, and join us in our mission to make this industry accessible to all, and prosperous for the long-term. We are offering access to the superyacht industry’s most comprehensive and longstanding archive of business-critical information, as well as a comprehensive, real-time superyacht fleet database, for just £10 per month, because we are One Industry with One Mission. Sign up here.
NEW: Sign up for
SuperyachtNewsweek!
Get the latest weekly news, in-depth reports, intelligence, and strategic insights, delivered directly from The Superyacht Group's editors and market analysts.
Stay at the forefront of the superyacht industry with SuperyachtNewsweek